Cmdlets for Zoho Projects

Build 24.0.9062

TaskMove

Moves a task from one tasklist to another tasklist. The target tasklist can be of the same project or different project.

Procedure-Specific Information

An example query for executing this stored procedure is shown below:
EXEC TaskMove PortalId = '12345317133', ProjectId = '123456000000031899', TaskId = '123456000000034053', FromTasklist = '123456000000031932', ToTasklist = '123456000000031941'

Input

Name Type Required Description
PortalId String True Specify the portal Id.
ProjectId String True Specify the group Id.
TaskId String True Specify the task Id.
FromTasklist String True Id of the tasklist in which the task exists.
ToTasklist String True Id of the tasklist to which the task has to be moved.

Result Set Columns

Name Type Description
Success String Specifies whether the execution was successful.

Copyright (c) 2024 CData Software, Inc. - All rights reserved.
Build 24.0.9062